Our People

Our People

Our Legal Services

Our Legal Services

Our Courses

Our Courses

Expert Legal Advice

This is a set of chambers providing barrister’s services in contract law and litigation. It provides assistance to solicitors and their clients. It also provides direct access services to businesses, organisations, local authorities and individuals who require legal advice and assistance with their legal issues, whether commercial problem solving, contract drafting or dispute resolution.

The practice includes barristers with expertise in contract law, company, commercial and civil disputes, intellectual property, competition & procurement, sale of goods, consumer rights, financial mis-selling, insurance, professional negligence, commercial property and construction.

We also offer continuing in-house legal services to companies who do not retain a legal department in order to advise on company-commercial issues, data protection, compliance and protection of their intellectual property including registration and dispute resolution.

Many of our clients use our training and consultancy services to get to know us and develop knowledge, CPD and bring lawyers and professionals together in an inter-active learning experience.

Chambers is authorised to conduct litigation directly without the necessity of instructing a solicitor. This means that you are able access expert legal advice without incurring significant additional costs that arise through the use of two lawyers working on the same case.

Legal Updates

31 Mar

That’s enough LADs: Court of Appeal concludes that liquidated damages may not be recoverable after termination

The facts of Triple Point Technology Inc -v- PTT Public Company Ltd are actually of little relevance here, save to note that Triple Point was engaged by PTT to provide certain software solutions under a contract that had key milestone dates and a provision for liquidated damages. The work was divided into key phases, and Triple Point achieved completion of Stages 1 and 2 of Phase 1 late and then continued to work on the remainder of the work. The parties then fell into dispute over the payment of invoices, Triple Point suspended the works and PTT terminated claiming Triple Point had wrongfully terminated. Although not a construction contract, it is easy to see how these facts are similar to scenarios which occur frequently on construction projects when a construction project goes wrong, it usually goes into delay before any termination. The employer will then be left trying to recover their losses which will include both the extra over cost of having another contractor complete the works and the losses stemming from delay.

Issues in dispute – when might LADs apply?

In the original case (before the TCC), the judge awarded $3,459,278.40 as liquidated damages for delay pursuant to Article 5.3 of the contract. On appeal, Triple Point argued that Article 5.3 was not engaged because that Article only applies when work was delayed, but nonetheless completed and then accepted by the employer. They submitted that the clause does not apply in respect of work which the employer never accepted, as in this case.

Sir Rupert Jackson considered three different options in respect of the validity of liquidated damages clauses in the event of termination of the contract, which I have converted into a visual for the purposes of this article:

LADs forever?

The Court of Appeal had no difficulty in rejecting option (iii), despite it having been preferred in Hall v Van der Heiden (N0 2) [2010] (a pure construction case) which was in turn followed by the High Court of Hong Kong in Crestdream v Potter Interior Design [2013] and, the High Court in GPP Big Field LLP v Solar EPC Solutions SL [2018] (regarding the construction of a solar facility). Sir Rupert Jackson held that “If they are correct, it means that the employer and the second contractor can control the period for which liquidated damages will run.” It will be of interest to readers to note that the relevant contract in Hall was a JCT Minor Works Building Contract (with contractor’s design).

Best of both?

The orthodox position was, arguably until this judgment, option (iii), where the measure of damages was split. There is considerable logic behind this interpretation but the Court noted that there are some difficulties, suggesting that “It may be more logical and more consonant with the parties’ bargain to assess the employer’s total losses flowing from the abandonment or termination, applying the ordinary rules for assessing damages for breach of contract.”

Sir Rupert Jackson concluded that option (iii) may apply, depending on the wording of the clause.

No LADs!

In the present case then, the Court of Appeal concluded that the wording of the relevant clause of the contract was inconsistent with an intention for it to apply in circumstances where the works were not completed by the original contractor. The Court followed British Glanzstoff Manufacturing Co. Ltd v General Accident, Fire and Life Assurance Co. Ltd [1912] in which the Court of Sessions had concluded that the clause allowing unliquidated damages on termination was an alternative to the remedy of liquidated damages for delay under clause 24.

It should be noted that again, Sir Rupert Jackson was keen to emphasise that this was a matter of the interpretation of the precise clause in the contract before the court: “In some cases, the wording of the liquidated damages clause may be so close to the wording in Glanzstoff that the House of Lords’ decision is binding. That is a decision of our highest court, which has never been disapproved.” He did, however, go on to conclude that the present case was one such case and that he considered Glanzstoff to be binding to the extent that the liquidated damages provision fell away in respect of works not completed at the point of termination. This meant that PTT could recover LADs for the late delivery of stages 1 and 2 of phase 1 but had to prove actual losses for the remainder of the works.

Another case of it depends

Sir Rupert Jackson and the Court of Appeal were charged with applying the law to the facts in respect of the specific case before them. The judgment does this in the clearest terms but does not, despite what some commentators may claim, set down new and conclusive rules about entitlement to claim LADs as apart of damages following the termination of a building contract. At paragraph 110 of the judgment, Sir Rupert Jackson stated “In my view, the question whether the liquidated damages clause (a) ceases to apply or (b) continues to apply up to termination/abandonment, or even conceivably beyond that date, must depend upon the wording of the clause itself. There is no invariable rule that liquidated damages must be used as a formula for compensating the employer for part of its loss.”

So what now?

If you are already in contract and the building works are in delay and you are considering terminating the contract (whether you are the employer or the contractor), it is important to get advice on all aspects of the prospective termination, including the likely basis of calculating damages for delay following this most recent judgment.

If you are not yet in contract and want certainty going forward, it is important to remember that the Courts will always look to give effect to the intentions of the parties when interpreting contracts. Clear and effective drafting in the schedule of amendments to your standard form building contract (or in your bespoke building contract) will be critical to ensure that you do not have any surprises in the event of termination coupled with delay.

16 Jan

Who has the burden of proof in bailment?

Volcafe Ltd and others (Appellants) v Compania Sud Americana De Vapores SA (Respondent) [2018] UKSC 61 On appeal from [2016] EWCA Civ 1103

Damage to coffee beans in transit. The Hague Rules must be read against the background of the common law rules on bailment . The Supreme Court reminded us of the two fundamental principles in the law of bailment: (i) a bailee of goods is only under a limited duty to take reasonable care of the goods, but (ii) the bailee nonetheless bears the legal burden of proving the absence of negligence.

 A contract of carriage governed by the Hague Rules is a contract of bailment unless excluded by the Rules and the Hague Rules do not exclude them.

The question of the burden of proof, which in accordance with ordinary principles of private international law are matters for the law of the forum .

The cargo owners brought a claim against the carriers for breach of their duties as bailees to deliver the cargoes in the condition recorded on the bill of lading and, alternatively, breach of article III, rule 2 of the Hague Rules for failure to “properly and carefully load, handle, stow, carry, keep, care for, and discharge the goods carried”. They alleged negligence by the carriers for failing to use adequate or sufficient Kraft paper.

The carriers pleaded “inherent vice” on the ground that the coffee beans were unable to withstand the ordinary levels of condensation forming on such a voyage.

The Supreme Court restored the judge’s factual findings (Donaldson LJ). Given the absence of evidence on the weight of the paper used, the Court decides that the carrier has failed to discharge its legal burden that it was not negligent.

Sitemap

Pages
News
×